Anglo Gold

Print this page
AngloGold
AngloGold
Ashanti Gold

Project

Anglo Gold Ashanti Sunrise Dam

Scope of Work

Design, manufacture, fully assembled (where practical) of one single new fabric filter baghouse to replace the existing deteriorate assembly currently installed at the existing plant.  The overall assembly was to fit within the pre-existing location to minimise site work and modification. 

Equipment Supplied

  • Engineering design of the new baghouse assembly
  • Supply of all ancillary equipment associated with the operation
  • Manufacture of all equipment, specially bags and cages
  • Ongoing services and spare parts

Details

Location

Laverton, WA

Project Duration

6 months

Completion Date

2018

Specifications

Gas Flow rate

36,000 Nm3/hr

Operating Temp

Ambient

Required Outlet Emissions

50 mg/Nm3

Filter Media

Bags and Cases assembly