Project
Moreton Bay Council Bio-trickling Filter System
Scope of Work
Design, supply, installation, commissioning and testing of an odour control system comprising Biological and Odorgard® stages at the Redcliffe Waste Water Treatment Plant.
Equipment Supplied
- Biological (1) scrubber
- Odorgard® (1) scrubber
- Nutrient Storage and dosing
- Instrumentation & includes outlet H2S monitoring
- Mechanical & electrical installation
- Commissioning
Details
Location
Redcliffe, QLD
Project Duration
6 months
Completion Date
2006
Specifications
Ventilation Rate
6,000 m3/hr
H2S inlet load
up to 200 ppmr
H2S outlet concentration
<0.05 ppm
Outlet odour concentration
<500 OU