Project
Redcliffe City Council – Redcliffe WWTP Odour Control System
Scope of Work
Design, manufacture, installation, commissioning of an Odorgard® scrubbing system at Redcliffe Waste Water Treatment Plant.
Equipment Supplied
- FRP Scrubber
- Odorgard® reactor
- Fan
- Recirculation pumps and piping
- Instrumentation
- Mechanical installation
- Access platform
- Commissioning
Details
Location
Redcliffe, QLD
Project Duration
6 months
Completion Date
2001
Specifications
Ventilation Rate
6,000 m3/hr
H2S inlet load
up to 20 ppm
H2S outlet concentration
<0.05 ppm