Project
Veolia CO2 Degassing system
Scope of Work
Design, supply and commissioning of CO2 degassing system for the reverse osmosis permeate at the water recycling facility at the Port Kembla.
Equipment Supplied
- CO2 (1) degassing system
- Forced draft (2) axial fans (duty/standby)
- Commissioning
Details
Location
Port Kembla, NSW
Project Duration
6 months
Completion Date
2003
Specifications
RO permeate flowrate
231 l/sec
Air flowrate
13,450 m3/hr
CO2 inlet load
45 mg/l
CO2 outlet concentration
<7 mg/l