WA Water Corporation – WA21 The Woodman Alliance Odour Control System.

​​Scope of Work

Design, manufacture and install Odorgard® scrubbing system at Woodman Point Waste Water Treatment Plant.

Equipment Supplied

  • FRP Scrubbers
  • Odorgard® reactors
  • Recirculation pumps and piping
  • Instrumentation
  • Dosing pumps
  • Access platform
  • Commissioning and performance testing
  • Operator training

Details

Location

Woodman Point, WA

Project Duration

12 months

Completion Date

2002

Specifications

Ventilation rate

24,000 m3/hr

H2S inlet load

up to 80 ppm

Inlet odour concentration

450,000 OU

H2S outlet concentration

max. 0.05 ppm

Outlet odour concentration

1000 OU