Project

Northern Water Plant Project  Forced Draft Co2 De-Gasser System

Scope of Work

Design, manufacture and deliver a CO2 De-Gasser system comprising a specifically designed FRP Forced Draft De-Gasser unit.

Equipment Supplied

  • Vessel c/w dual spray headers
  • Axial (2) fans with inlet silencers
  • Inlet plenums with filter housings
  • Pressure Instrumentation
  • Interconnecting ducting with supports
  • Sump Vessel

Details

Location

North Geelong (Corio), VIC

Project Duration

4 months

Completion Date

2012

Specifications

Inlet flow rate

67.2 L/s

CO2 removal efficiency

≥90%

Sump Capacity

40m3