Project
Cockburn Cement ESP Refurbishment
Scope of Work
For the refurbishments of ESP located at the Munster Plant. The refurbishments are to ensure emission compliance and continuous operation during normal operations.
Equipment Supplied
- Inspection and investigation works
- Site management of works inclusive of mobilisation and demobilisation
- Mechanical Repairs
- Electrical/Control Upgrades
- Performance testing and commissioning
Details
Location
Munster, WA
Project Duration
3 months
Completion Date
2005
Specifications
Gas Flow rate
144,000 Nm3/hr
ESP Manufacturer
Not Available
Inlet Dust burden
150 g/Nm3
Emission Levels
50 mg/Nm3 (max)