



Project
Sydney Water Corporation Odorgard® scrubbing system
Scope of Work
Design, manufacture and install Odorgard® scrubbing system at Glenfield Sewage Treatment Plant.
Equipment Supplied
- Civil works
- FRP covers and ducting
- Scrubbers
- Odorgard® reactor
Details
Location
Glenfield, NSW
Project Duration
18 months
Completion Date
2000
Specifications
Ventilation rate
36,000 m3/hr
H2S inlet load
up to 5 ppm
Inlet odour concentration
50,000 OU/sec
Outlet odour concentration
500 OU/sec
