Project

Onesteel Newcastle Electroplating Facility Fume Extraction and Wet Scrubbing System

​​Scope of Work

Design, detail engineering, procurement, manufacture and supply fume extraction/wet scrubbing system for installation at Onesteel electroplating facility at Newcastle.

Equipment Supplied

  • Scrubbing vessels, 3.4m dia, 7.25m high packed tower with 10m stack
  • Interconnecting Ducting
  • Fume extraction fans
  • Recirculation and chemical dosing pumps
  • Valves, instrumentation and piping

Details

Location

Newcastle, NSW

Project Duration

6 months

Completion Date

2002

Specifications

Gas flow rate

87,000Am3/hr

HCI/NO2 inlet load

100ppm

HCI/NO2 outlet load

10ppm